IDBZ shelves Gwayi, Plumtree solar projects

Published

on

HARARE – The Infrastructure Development Bank of Zimbabwe (IDBZ) says it is shelving two solar power projects of a combined 45MW because of Zesa’s poor transmission infrastructure.

IDBZ will no longer pursue the 15MW Tjibundule solar project in Plumtree, Matabeleland South, whose estimate cost is US$23 million.

Advertisement

The bank has also abandoned plans to set up the 30MW Gwayi Solar Project in Matabeleland North, which had been projected to cost US$45 million.

“The bank has noted that inadequate transmission and distribution infrastructure will negatively affect the scaling up of renewable energy projects across the country,” said IDBZ CEO Zondo Sakala.

“Grid impact assessments have shown that existing substation and transmission infrastructure will not be able to accommodate some of the Bank’s planned solar projects…hence the Bank’s decision to shelve them.”

Advertisement

Some “alternative suitable sites for the implementation of the envisaged solar projects” are now being looked at, IDBZ said in its latest half-year financials.

While Zimbabwe is scaling up investment in generation capacity, there has not been equal investment in replacing aged transmission infrastructure.

This may further hurt new energy investment, already limited by the country’s currency and regulatory hurdles.

Advertisement

According to a report in 2019, Zesa loses almost 20 percent of its power due to aged transmission and distribution infrastructure.

Solar projects are among IDBZ’s priority infrastructure investment areas. While the Plumtree and Gwayi projects have stalled, IDBZ is still invested in the 50MW Rufaro Farm solar project at Longlands Farm outside Marondera.

The bank is also investing in a 20MW plant in Gutu, as well as mini hydros on the Osborne and Odzani rivers.

Advertisement

In July, IDBZ received accreditation to the Green Climate Fund, which helps in channelling investment in renewable energy.

The bank, like many other local and foreign investors, is facing frustrating red tape in its attempts to get projects off the ground.

“Completion of project preparatory work is also being delayed by the time needed to obtain the required regulatory approvals,” the bank said.

Advertisement

The bank needs the equivalent of US$2.5 million to prepare and start developing the projects that it has targeted as priorities in 2021.

“In the outlook, the Bank is buoyed by positive economic prospects, macroeconomic stability, an increased focus on infrastructure investment by Government,” said IDBZ. – newZwire